Xylem Hydrovar X 4-Pump Booster Set Installation
The existing set was hanging on by a thread and had caused multiple water outages in the last 12 months. It was end of life and due for replacement.
We re-sized the set appropriately for the building and thanks to this and the Hydrovar X increased energy efficiency were able to drop it to a more appropriate 4-pump set.
We completed the works in normal hours in one day, during a planned water outage. This included modifying the DN150 pipework to DN100 and a 54mm bypass, new expansion bellows and isolation valves.
The Xylem Hydrovar X is a smart upgrade in this instance and provided the most cost effective solution for site.
More fantastic work from our engineers Andy Shelley, Antony Chesters, Carl Rogerson, Kieran Shields and John Murphy (all hands on deck!).