The background:
These jobs were carried out at 3 different hotels in Bournemouth. All 3 units were u/s and in need of replacement. As a result, PressBoost installed all 3 units in a 2 day trip, thus, by combining the 3 jobs into such a small time frame we managed to save on labour and travelling expenses for the customer.
As you can see from the pictures below, the original installations were ageing and/or piston pumps. PressBoost installed 1 x floor mounted Presfix Beta MKII and 2 x wall mounted Mini Presfix, these both benefit from digital controls and peripheral turbine pumps and the ease of access for maintenance is excellent.
The Before and After:
The logistics:
As you can see from the pictures above, the access to install these units was challenging, however, we are able to fully retrofit all replacement units to suit the requirements of site. We have a variety of unit options to suit the requirements of site as well of a variety of sizes. Additionally, although we are based in Manchester, we operate nationwide so please do not hesitate to get in contact if you have any queries!